Part Lead Time Horizon Only

Training Manuals Alphabetical Function List Back Print this Topic Previous topicOne level upNext topic

When unchecked, all requirements for the selected part, irrespective of the required date, will be taken into account, unless such dates have been specified in the "From" and "To" fields, in which case, only requirements with a required date falling within this range will be taken into account.

 

When checked, the function will limit the "To" date to the (current date + part lead time days), with the result that, only requirements that fall within the lead time horizon will be taken into account.  The part lead time days are work days and can be viewed on the Detail tab.